BSS Cloud Migration Phase 1 - 95-100% complete. This was the ‘AS IS’ Moving to Phase 2, which is developing the functional spec for what we want the solution to include.
Data API - Frank to give the okay once Data API is up and running in SB2
SB2
NRESR-Phase 1
POAW-
Boostr
Leslie
Weekly IT and ENG Status Report (please complete data from weeks ending 8/9)
Thanks all for keeping up to date!
IT Time tracking report
Weekly status reports- projects status
MS Teams , voice equipment, training
CROSS-CAP
Jira - Portfolio please hold off on updating/ connecting your projects More to come
working remote 8/14-8/16
Frank
Traffic Upgrade - starting this week - storage is ready in Rackspace
CAP-NT02 - added 2 new drives - moving files this week to improve performance
Geckoboard, 1st phase of API Integration project are wrapping up soon. Campsite API seems to be working ok so we’re moving forward with integrating inventory with them.