Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Discussion topics

Presenter

Notes



Abe

  • Continued Looker UAT coordination for CoreValue Reporting Migration Project

  • Real Estate Sales Ops Looker development - weekly meetings with Matt and Will to make sure their needs are being met; committed time to collaborate

    • Completed Financial revenue data model with accounting periods (time)

    • In progress: derived table for automated comparison against budget (static table for now)

      • Done: Revenue, Budget, Revenue vs Budget delta, aggregated budget, aggregated delta, % delta, % delta aggregate

      • In progress: year-over-year comparison of revenue

    • Next steps: collaborate with Elisa on automating the Budget out of netsuite; currently budget is a static table that I uploaded in Snowflake (thanks again to Frank for restoring some rights for me)

    • backlog:

      • troubleshooting outlook meeting sync with NetSuite in Looker

Action items

  •  

Decisions