Presenter | Notes |
---|
Karen | BSS Cloud Migration Phase 1 - 95-100% complete. This was the ‘AS IS’ Moving to Phase 2, which is developing the functional spec for what we want the solution to include. Developing tagging strategy for AWS environment. Building out AWS environment.
|
Andrea | Clear the Sandbox! SB1 SB2 NRESR-Phase 1 - began regression testing 8/12/19 POAW- UAT with Finance Monday/Tuesday; feedback to CV for regression testing Boostr - need to confirm the connection between Boostr and NS-SB2; ensure API generates a Purchase Order
Develop new Path to Production for SB1, SB2 & Production - implement a process for DEV, QA/UAT, Move to Production Scope next CV project - Jira Tickets
|
Leslie | Weekly IT and ENG Status Report (please complete data from weeks ending 8/9) Thanks all for keeping up to date! IT Time tracking report Weekly status reports- projects status MS Teams , voice equipment, training CROSS-CAP Jira - Portfolio please hold off on updating/ connecting your projects More to come working remote 8/14-8/16
|
Frank | Traffic Upgrade - starting this week - storage is ready in Rackspace CAP-NT02 - added 2 new drives - moving files this week to improve performance Geckoboard, 1st phase of API Integration project are wrapping up soon. Campsite API seems to be working ok so we’re moving forward with integrating inventory with them. Welcome Roshan!
|
Abe | |