Karen

  • BSS Cloud Migration Phase 1 - 95-100% complete. This was the ‘AS IS’ Moving to Phase 2, which is developing the functional spec for what we want the solution to include.

  • Developing tagging strategy for AWS environment.

  • Building out AWS environment.

Andrea

  • Clear the Sandbox! SB1

    • Remaining items - CRM Migration - Pending Stacey Driscoll Stacey’s ok re: saved searches

    • Data API - Frank to give the okay once Data API is up and running in SB2

  • SB2

    • NRESR-Phase 1 - began regression testing 8/12/19

    • POAW- UAT with Finance Monday/Tuesday; feedback to CV for regression testing

    • Boostr - need to confirm the connection between Boostr and NS-SB2; ensure API generates a Purchase Order

  • Develop new Path to Production for SB1, SB2 & Production - implement a process for DEV, QA/UAT, Move to Production

  • Scope next CV project -

    • Roles & Permissions/clean up unused datafields

    • Cloud Migration

    • Go Stick (question) I have an open Jira ticket with several updates/requests from MS requesting Go Stick set up (items,

  • Jira Tickets

Leslie

  • Weekly IT and ENG Status Report (please complete data from weeks ending 8/9)

  • Thanks all for keeping up to date! (smile)

  • IT Time tracking report

  • Weekly status reports- projects status

  • MS Teams , voice equipment, training

  • CROSS-CAP

  • Jira - Portfolio please hold off on updating/ connecting your projects More to come

  • working remote 8/14-8/16

Frank

  • Traffic Upgrade - starting this week - storage is ready in Rackspace

  • CAP-NT02 - added 2 new drives - moving files this week to improve performance

  • Geckoboard, 1st phase of API Integration project are wrapping up soon. Campsite API seems to be working ok so we’re moving forward with integrating inventory with them.

  • Welcome Roshan!

Abe

  • Looker UAT continued follow-ups and passes

    • ‘Next Gen’ project discoveries

  • Real Estate Sales Ops development

    • Financial Actual Income data model

    • State Change dimension analysis: time spent in / between phases

    • Outlook Meeting info

Stacey

  • CRM to NetSuite

    • Case Parts into SB2

    • Finish list of issues

  • Vistar Weekly Report

  • Campsite Weekly Report

  • Revenue UAT

  • If time: Continue Looker Training